Want a new kitchen by spring 2027? The best time to start is now. Not because demolition takes forever, but because of everything that has to happen before anyone picks up a crowbar. Most of a kitchen remodel's calendar goes into decisions, not construction.
Here's the four-step cabinet timeline we walk our Denver clients through: measure, design, samples, order. The trick is to work backward from the month you want to be cooking in your new kitchen.
Step 1: Measure (and pick your appliances)
Measure every wall, the ceiling height, and exactly where the windows, doors, plumbing, vents and outlets sit. A few habits that save headaches later:
- Measure each wall at three heights. Older homes are rarely square, and a wall that's an inch wider at the floor than at the ceiling changes your cabinet plan.
- Photograph each wall straight on. Your designer will thank you.
- Choose your appliances first. Cabinets are sized around them, and two inches really does matter.
Our kitchen measurement checklist walks you through every number to grab.
Step 2: Design
This is where the layout, storage and budget come together. Drawers or doors? Where does the trash pull-out go? Does the island get seating? Give yourself a few weeks here, because good designs go through a few rounds of revisions.
It's also when you choose your cabinet line. We carry five (CNC, Kith, Nations, Cabinet Corp and JSI), and they land at very different price points. A basic cabinet quote from Koda is free, so you can compare before you commit.
Step 3: Samples
Never pick a cabinet color from a screen. Get a real sample door and live with it for about a week, in your own light, next to your countertop and flooring samples. Look at it in the morning, at noon and at night. Colors shift more than you'd think, especially with Colorado sunshine pouring in.
You can order sample doors from any of our five lines to keep while you design.
Step 4: Order
Once the design is signed off, the order goes in. Stocked lines can arrive in a few weeks; built-to-order lines usually take about four to six weeks, sometimes longer depending on the finish. Book your installer now, too.
When the cabinets arrive, check every box against the order before installation starts. A missing panel is far easier to sort out before your old kitchen is torn out.
Don't forget the rest of the room
- Talk to your contractor early. Spring is busy in Denver, and good installers book up fast.
- Plan for countertops. They're templated after the cabinets go in, which can add one to three weeks.
What a spring 2027 kitchen timeline looks like
- November to December: measure, and choose appliances
- Through January: design and revisions, pick your cabinet line
- January: live with your sample doors
- February: place the cabinet order, book your installer
- March: cabinets arrive, install, then countertop templating
- Spring: cooking in your new kitchen
Three mistakes that cost you weeks
- Ordering before the design is final. Changes after the order goes in mean delays and extra cost.
- Picking colors from a screen. Screens lie. Samples don't.
- Waiting until spring to start. By then, you're competing with everyone else for designers, installers and delivery slots.
Want help building your timeline?
Planning a kitchen or bath for 2027? Book a free design chat and we'll build your timeline, compare cabinet lines with you, and get sample doors in your hands, so you start the new year with a plan.